Installation of sewer pipeline between manholes # 1 and #2, after TTEC secured the underground high-voltage cable. (Image courtesy Water and Sewerage Authority)

Work on the final phase of the Beetham Sewer Pipeline Project is progressing as planned after the team from T&TEC completed securing the underground high-voltage cable in the pathway between the two newly installed manholes, on Monday 24th January 2022.

That’s according to another advisory issued today by the Water and Sewerage Authority, seeking to provide the public with a Progress Report on the project.

WASA estimates that completion of works is expected to be deferred by no more than one week.

“The Authority is working assiduously towards completing these works at the earliest to minimize the inconvenience to the residents of Beetham and will continue to issue ongoing updates as key milestones are achieved,” the WASA advisory said.

WASA explains the project is progressing with the installation of the pipeline to connect manholes #1 and #2, as well as installation of the third and final manhole.

The Authority notes this will be followed by the reconnection of two sewer lateral connections; interconnection of the new pipeline system; and finally, remedial and restoration works, inclusive of permanent road restoration.